Wellington photovoltaic energy storage project completed
Ampyr Australia, the local arm of Singapore-based developer Ampyr Energy, has achieved financial close for its 300 MW / 600 MWh Wellington stage one battery energy storage system project being developed in central west New South Wales.
[PDF Version]
-
Wellington Mobile Energy Storage Project
[Sydney, 14 October 2022] AMPYR Australia Pty Ltd (AMPYR) and Shell Energy Australia (Shell Energy) have signed a joint development agreement for a proposed battery energy storage system strategically located in Wellington (the Wellington BESS), Central West New South Wales (NSW).
[PDF Version]
FAQS about Wellington Mobile Energy Storage Project
What is the Wellington Battery energy storage system (BESS)?
The Wellington Battery Energy Storage System (BESS) is planned to be developed in the central west New South Wales (NSW), Australia. The project will comprise a grid-scale BESS with a total discharge capacity of around 400MW. AMPYR Australia, a renewable energy assets developer in the country, owns 100% of the BESS project.
Where is Wellington South Battery energy storage system being developed?
Wellington South Battery Energy Storage System is being developed in NSW, Australia. (Credit: Sungrow EMEA on Unsplash) The Wellington Battery Energy Storage System (BESS) is planned to be developed in the central west New South Wales (NSW), Australia. The project will comprise a grid-scale BESS with a total discharge capacity of around 400MW.
What is the target capacity of the Wellington Bess?
The target capacity of the Wellington BESS is 500 MW / 1,000 MWh, making it one of the largest battery storage projects in NSW. The Wellington BESS will connect to the adjacent TransGrid Wellington substation, adjacent to the Central West Orana Renewable Energy Zone (Central West Orana REZ).
When will the Wellington substation be built?
Construction of Stage 1 (300MW / 2 hours) will start mid-2025, finishing early 2027. Plans for construction of Stage 2 are ongoing, but construction is likely to follow 12 to 18 months behind Stage 1. The existing Wellington substation is very strategically located within the NSW energy grid.
Which is the largest battery storage project in NSW?
This will make Wellington BESS one of the largest battery storage projects in NSW. Wellington is being constructed at 6773 and 6909 Goolma Road, Wuuluman NSW 2820. The project site is situated within the Central-West Orana Renewable energy Zone (CWO REZ), in the Dubbo Regional Council local government area (LGA).
How will the Wellington Bess project be developed?
The Wellington BESS project will be developed in two stages. The first stage will have a capacity of 300 MW / 600 MWh, while an additional 100 MW / 400 MWh capacity to be added in the second phase.